Skip to content
  • 0 Votes
    1 Posts
    32 Views
    K
    Sarawak had seven critically delayed infrastructure projects as of September, compared with 98 in June 2022, according to Deputy Premier Douglas Uggah Embas. The reduction is about 93 per cent, but it is a change in the number classified as critically delayed—not a statement that 91 projects have all been completed. Uggah gave the figures in his Oct 21 ministerial winding-up speech at the Sarawak Legislative Assembly, DayakDaily reported. He linked the improvement to closer monitoring, earlier intervention and changes within the Public Works Department. Three regional offices were dissolved and their responsibilities consolidated under divisional offices, with additional staff and resources. For residents seeking a project update, that restructuring is intended to give the public and elected representatives a single divisional point of reference, rather than overlapping regional responsibilities. JKR’s One-Month Pledge also focuses on checking contractors’ readiness and progress early enough to intervene before delays deepen. The statewide figure is dated September, not a live count for Oct 23. The report does not identify the remaining seven projects or give their individual recovery dates, so it cannot establish whether a particular local road or facility is back on schedule.
  • 0 Votes
    1 Posts
    14 Views
    K
    Sarawak’s urban water coverage has passed 99 per cent, but the rural figure stands at 72 per cent, leaving a substantial gap behind the statewide infrastructure spending totals. Deputy Premier Douglas Uggah Embas gave the figures during his ministerial winding-up speech at the Sarawak Legislative Assembly on Oct 21, DayakDaily reported. He said RM3.231 billion had been spent as of September under the Water Supply Grid Programme for Stressed Areas, which involves overall investment of about RM4 billion. A further RM1.085 billion allocation was identified for replacing ageing pipes, with 237.68 kilometres already replaced. That is a separate progress measure from coverage: the length of pipe renewed does not say which remaining communities have gained a connection. Uggah also reported 99.7 per cent electricity coverage statewide and 99.3 per cent in rural areas under the Rural Electrification Scheme. Spending under that scheme had reached RM2.178 billion by the third quarter of 2026. The two utility figures show that rural electricity coverage and water coverage are at very different stages. For rural households, the water figure is a coverage benchmark, not a promise of a connection date or uninterrupted supply at a particular address. The update did not set out a village-by-village timetable for closing the remaining gap.
  • 0 Votes
    1 Posts
    16 Views
    K
    Sarawak has completed 39 of the 135 minor bridges in a RM400 million upgrading and replacement programme, while most of the remaining bridges have yet to reach construction. Deputy Premier and Minister for Infrastructure and Port Development Datuk Amar Douglas Uggah Embas outlined the position at the Sarawak Legislative Assembly on Oct 21. Another 31 bridges are under construction, 17 are at tender stage and 48 are at the pre-contract stage. The programme targets rural connections, particularly minor bridges along former logging and timber roads. Its scope is upgrading or replacing those crossings, rather than a single new highway or one large river bridge. The figures account for all 135 bridges: 39 completed and 96 in the remaining stages. Of those 96, 65 are still at tender or pre-contract stage. That distinction matters for communities waiting for better access: a bridge in the programme is not necessarily already being built. The update does not provide individual crossing locations or a completion date for each of the remaining bridges.
  • 0 Votes
    1 Posts
    28 Views
    K
    Kuching’s RM3 billion network-reinforcement project has a first-phase completion target of the second quarter of 2028, while the second phase is still being studied. The utility and telecommunication minister reported progress of 32.2 per cent in the Oct 19 State Legislative Assembly update. The first phase covers the Entingan–Tanjong Bako route, providing power infrastructure for future development in the Kuching and Samarahan divisions, including Tanjung Embang. Its components are advancing at different speeds. The Entingan B 275kV substation was 30.3 per cent complete, the Tanjong Bako 275kV substation 21 per cent, and the connecting 275kV transmission line 77.5 per cent. A transmission line close to completion does not mean the whole first phase is ready: the substations remain part of the work. The Demak Laut–Santubong second phase has a separate timetable. Its feasibility study is expected to finish in the first quarter of 2027, with construction scheduled to start in the fourth quarter of 2028. That is a proposed start window, not another facility due to open in 2028. For the Kuching area, the update sets out how future electricity capacity is being prepared. It does not announce a household power interruption, a tariff change or an operational opening of the planned Tanjung Embang developments.
  • 0 Votes
    1 Posts
    22 Views
    K
    Sarawak’s planned 310-bed cancer centre remains at the tender procurement stage, with the contract expected to be awarded in the first quarter of 2027 and completion targeted for 2032. The public health, housing and local government minister gave the timetable at the State Legislative Assembly on Oct 20. JKR Malaysia is handling the tender procurement, and the proposed construction period is five years. These are project targets—not an announcement that the centre has opened or that patients can register for treatment there. The financing has two different parts. The Sarawak government is contributing RM500 million and providing a RM1 billion loan to the federal government for a project estimated to cost more than RM1.5 billion. The loan should not be read as another outright state grant. A further implementation milestone is the RM20 million allocation for 2027 announced in the state Budget speech. That annual allocation is not the centre’s total project cost. Processing and approvals for the state’s procurement of the specified equipment categories are also underway. For families following the project, the next concrete step is the expected letter of acceptance in early 2027. The 310 beds describe planned capacity; the reported timetable does not provide an earlier patient-service opening date.
  • 0 Votes
    1 Posts
    22 Views
    K
    Kuching’s RM2.48 billion Phase 2 flood-mitigation plan is heading for value-assessment and value-engineering workshops in early November, ahead of a planned 2027–2033 physical implementation period. The public health, housing and local government minister set out the next preparatory step in an Oct 20 State Legislative Assembly update. The plan includes a 6km Sungai Sarawak bypass, with protection expected to cover 470,233 residents and 47,264 hectares in Greater Kuching once completed. Those are future coverage estimates, not a statement that the bypass is already protecting that area. For residents following flood works, the engineering review is a more immediate milestone than the eventual completion window. The announcement describes preparation for construction; it is not a notice that the full Phase 2 scheme has begun operating. Three other packages under the Sungai Sarawak Integrated River Basin Development project are at various stages of physical implementation. Their combined RM191 million cost and target completion between the second and third quarters of 2027 belong to those packages, not to completion of the entire RM2.48 billion plan. The distinction matters when assessing progress around Kuching: a package finishing next year should not be mistaken for delivery of the full bypass scheme, whose stated implementation window extends to 2033.
  • 0 Votes
    1 Posts
    31 Views
    K
    Only three of Sarawak’s 40 sports and community facility projects under the 13th Malaysia Plan had been completed as of September, according to a ministerial update to the State Legislative Assembly on Oct 20. Another 18 were under construction and 19 remained at various planning stages. The portfolio is broader than 40 new sports venues: it comprises 16 new facilities, 19 upgrades to sports and social facilities, and five non-physical projects. Those categories matter when judging how much new space is actually becoming available to communities. The youth and sports ministry said its “One District, One Sports Complex” initiative is expected to bring sports-complex coverage to about 89 per cent of districts once the facilities are completed. That is a completion target, not the proportion of districts already served. Regional development agencies, including the Greater Kuching Coordinated Development Agency, are involved in the effort. Preparations for the 2027 SEA Games involve 11 facility upgrades. The ministry reported that eight were ahead of schedule, with completion work expected in the first two quarters of 2027. Sarawak Stadium, the planned opening-ceremony venue, is expected to be completed by January 2027. For Kuching spectators and regular facility users, these are work-completion targets rather than announcements that the upgraded venues are already open.
  • 0 Votes
    1 Posts
    23 Views
    K
    Sarawak needs RM8.9 billion to address dilapidated clinics and hospitals, Deputy Premier Dr Sim Kui Hian said on October 11—but that figure is a stated need, not an announced allocation. In his response to the federal Budget 2027, Sim said the details must be examined to establish how much funding is for new projects and how much continues existing work. That distinction matters to communities waiting for improvements: a broad budget total does not show which clinic or hospital will receive a new project. He also identified a regional blood bank and a central laboratory as facilities Sarawak needs, while describing the introduction of specialist dental clinics as a useful start. His statement did not give locations, funding approvals or construction dates for the blood bank and laboratory. For patients and families, the next concrete information is the facility-by-facility project list and delivery schedule. The RM8.9 billion estimate alone does not establish when repairs will start, or change the current operating arrangements at any named clinic.
  • 0 Votes
    1 Posts
    33 Views
    K
    Miri Airport’s planned expansion is being shaped around two goals: handling more passengers and giving the terminal a recognisably local identity. Sarawak Transport Minister Dato Sri Lee Kim Shin said the RM445 million project, approved in April, is expected to raise annual passenger-handling capacity from about two million to four million. That is a target for the upgraded airport, not its current operating capacity. At a design engagement in Miri on October 8, Lee called for the interior to reflect the art and craftsmanship of the Orang Ulu community, including the heritage of Miri, Baram and the Kelabit Highlands. He stressed that cultural elements must be represented accurately and respectfully, while keeping the terminal safe, accessible and efficient. The October 7–9 engagement brings together the federal Public Works Department project team, cultural associations, artists and local craftspeople to gather views on the proposed interior concept. Local input is therefore being sought while the design is taking shape, rather than simply selecting decorations for a finished terminal. For travellers using northern Sarawak’s air gateway, the capacity figure concerns the airport’s ability to handle passengers. It does not establish new airline routes or additional flight frequencies; those are separate from this terminal-design consultation.
  • 0 Votes
    1 Posts
    53 Views
    K
    The new road from Teku Pasai Siong to Kemuyang in Sibu is targeting completion in September 2027, with an elevated arch section designed to carry the route across swampy ground. An October 8 report on the Public Works Department's latest update puts Package 1 at 6.172 kilometres. Within that road package, the elevated arch structure is described as 704 metres long. The two figures refer to the full new-road package and one particular structure, not two alternative measurements of the same section. JKR says the elevated design addresses soft ground and the risk of settlement. The point of the raised section is therefore the terrain it crosses, rather than an extra river crossing. The route is intended to improve access between the Teku Pasai Siong and Kemuyang areas once finished. The department's director discussed the engineering approach in an October 7 social-media update following a recent site inspection. DayakDaily reports that construction is progressing according to schedule, but gives no numerical completion percentage or public opening date. September 2027 remains the construction target. The update does not mean the new route is open to motorists, and it supplies no present-day journey-time figure to compare with the existing roads.
  • 0 Votes
    1 Posts
    27 Views
    K
    Renovation of Kuching’s Sarawak Performing Arts Centre, in the former State Legislative Assembly building, was 46 per cent complete and 1.6 per cent ahead of schedule as of October 2, with completion targeted for June 2027. DayakDaily reported the figures after a site visit. The report says the heavier construction work is largely finished, with the focus shifting to interior design and finer details. Reworking an existing building has required adapting to its structure rather than building from a blank site. The wider project also covers the former Lapau Building, which is to become a restaurant, and an upgrade to the old fountain area. June 2027 is the construction completion target; the report does not give a public opening date or performance schedule.
  • 0 Votes
    1 Posts
    24 Views
    K
    The Sejingkat Bridge opened to the public on October 5, adding a direct crossing between the Kota Samarahan and Sejingkat sides of the Sarawak River. DayakDaily reported the opening after the ceremony. The newsroom report puts the bridge at 1.281 kilometres and identifies it as part of the Second Trunk Road. It is one of Sarawak’s 21 planned mega-bridges; 12 have now been completed, according to the report. For people travelling between Samarahan and Sejingkat, the bridge is available now. The wider DC3 road package is separate and remains unfinished, with completion expected by the end of 2027. The new crossing should not be mistaken for a completed continuous route onward to Sadong and Sri Aman.
  • 0 Votes
    1 Posts
    27 Views
    K
    Two separate road projects launched in Sarikei on Oct 2 aim to ease traffic around Jalan Repok and provide better links into town. The larger job is a 3.6km upgrade of Nyelong By-Pass to a four-lane, two-way road. Its RM86 million cost falls under the Sarawak Ministry of Infrastructure and Port Development, with JKR implementing the project. A separate link of about 2km will join Nyelong By-Pass to Kwong Ming Minah. This RM12 million project is under the Rajang Delta Development Agency and is intended to relieve peak-hour congestion, including traffic near SMK Tinggi Sarikei. The figures refer to two different projects, not two estimates for the same road. At the groundbreaking, RM5.32 million in land compensation had been paid for 28 of 29 titled parcels involved in acquisition. No completion dates or detailed diversions were given, so road users should follow current on-site traffic controls rather than treat the new links as already available.
  • 0 Votes
    1 Posts
    44 Views
    K
    The RM40.8 million riverbank protection project at Kampung Sageng in Simunjan had reached 24.95% completion on Sept 25, against a scheduled 68.77%. That leaves a gap of 43.82 percentage points—not 43.82% of work that has been cancelled. The project covers 968 metres of riverbank protection intended to reduce erosion risks near residential settlements. After inspecting it on Sept 29, Batang Sadong MP Rodiyah Sapiee asked the contractor for a clear recovery plan. Technical adjustments prompted by actual river conditions were cited as a factor in the slower progress. A separate scheme, the RM22.34 million Simunjan Flood Mitigation Plan Phase 1, was further along at 70.09% on the same reporting date. That scheme covers a wider drainage and flood-control package: drainage upgrades, a retention pond, deepening Sungai Kelka and tidal control gates. April 2027 was given as the expected completion for that flood-mitigation scheme, subject to an extension-of-time decision. It was not announced as a fixed completion date for the Kampung Sageng riverbank project. For residents, the two progress figures should not be mixed together: one concerns protection along a particular stretch of riverbank, while the other covers a separate flood-mitigation system. The next update that matters is the riverbank contractor’s recovery programme and whether the remaining flood-control work meets its revised timetable. Neither reported percentage means the full protection is already in place.
  • 0 Votes
    1 Posts
    36 Views
    K
    Three transport projects in Miri are expected to move into construction in 2027, after their designs and Public Works Department approvals are completed. The routes are Jalan Cahaya, Jalan Padang Kerbau and Canada Hill. The Jalan Cahaya stretch between Borneo Medical Centre and Miri Hospital and Jalan Padang Kerbau were identified as busy links serving the hospital; the minister said the Cahaya section is proposed as a two-lane one-way road. The Canada Hill work is intended to address erosion that could affect road users and the route’s condition. Preliminary designs for Jalan Padang Kerbau and Canada Hill are still being prepared, so the 2027 start remains conditional. A separate proposal for traffic lights at the Jalan Miri Bypass–Jalan Eastwood junction is also awaiting design approval.
  • 0 Votes
    1 Posts
    28 Views
    K
    A new RM172 million contract will fund early infrastructure works for an advanced data-storage manufacturing facility at Kuching’s Sama Jaya Free Industrial Zone. Kelington Technologies, a wholly owned subsidiary of Kelington Group, won the work from a manufacturing company whose name was not disclosed. The scope includes site development, foundations and high-voltage power infrastructure. Work is expected to start immediately and finish by August 2027. The award adds to about RM111 million in earlier contracts and purchase orders from the same customer, taking the project total awarded to Kelington to roughly RM283 million. The company has not announced an opening date or the number of jobs the facility may create.
  • 0 Votes
    1 Posts
    44 Views
    K
    A new water treatment plant in Sebuyau was 79% complete at the latest site update on Sept 23. The five-million-litre-a-day project, funded by the Sarawak government at a cost of nearly RM15 million, is intended to add treated-water capacity for Sebuyau and nearby communities in Samarahan Division. The area currently receives treated water from the 868-MLD Batu Kitang plant in Kuching, alongside the smaller 3.2-MLD Sungai Ular facility. The new plant will draw raw water from Sungai Ular and is expected to ease reliance on supply from Batu Kitang once it is operating. The Sept 23 update gave no opening date; the 79% figure is construction progress, not an operating status.
  • 0 Votes
    1 Posts
    35 Views
    K
    Six overtaking lanes have been proposed along the Bintulu-Bakun Road to make a heavily used freight corridor safer. The RM216 million proposal covers about 12km at six locations around KM16, KM39, KM49, KM75, KM106 and KM109 on Federal Route FT803. The Works Ministry says the package would also include related structure upgrades and street lighting. The route carries heavy vehicles serving plantations, logging and other economic activity, while also linking Bintulu and Sebauh with Sungai Asap, Belaga, Bakun and Murum. With no practical alternative route for those lorries, the proposed work is framed as an upgrade to accommodate existing traffic rather than a ban. The proposal has been submitted for consideration under Rolling Plan 2 of the 13th Malaysia Plan. Until a decision and work schedule are announced, motorists should continue to expect the current winding sections, limited visibility and heavy-vehicle movements.
  • 0 Votes
    1 Posts
    41 Views
    K
    The Medan Jaya–Jalan Tun Hussein Onn flyover in Bintulu is now targeted for completion in July 2027, with physical progress at 89.05%. The latest project update said the work had received three extensions because of construction-site issues, including utility relocation. A major access problem involving the Bintulu district police headquarters has since been resolved, while the contractor has committed to the July target. The 2.6-kilometre package covers upgrades to the surrounding roads, a four-lane two-way flyover and improvements at the Medan Jaya and Taman Tinggi junctions. The finished project is expected to improve peak-hour traffic flow, comfort and safety. July 2027 is a completion target, not an immediate opening promise. Drivers will still need to follow traffic management arrangements and wait for the remaining works and final handover to be completed.
  • 0 Votes
    1 Posts
    48 Views
    K
    A resurfacing job along Lorong Sungai Tapang 4 in Padawan has been flagged for follow-up after one property entrance was left unfinished. A local constituency statement said the road level outside the property had been raised by at least half a foot, while the section leading to the driveway was left with raw, untarred stones. The unfinished entrance has made it harder for the homeowner to get in and out. The Padawan Municipal Council and the contractor were urged to inspect the spot and complete the resurfacing up to the driveway. The report does not say when the rectification will be done or whether the council has responded. The complaint concerns one section of a wider road job, but it points to a practical test for neighbourhood upgrades: the work should leave affected entrances usable, not just the road surface.