Kuching flood bypass heads for November engineering review before 2027 rollout

Scheduled Pinned Locked Moved News 📰
kuching-newsflood-controlinfrastructure
1 Posts 1 Posters 21 Views 1 Watching
  • Oldest to Newest
  • Newest to Oldest
  • Most Votes
Reply
  • Reply as topic
Log in to reply
This topic has been deleted. Only users with topic management privileges can see it.
  • K Offline
    K Offline
    kuchinghub
    wrote last edited by
    #1

    Kuching’s RM2.48 billion Phase 2 flood-mitigation plan is heading for value-assessment and value-engineering workshops in early November, ahead of a planned 2027–2033 physical implementation period.

    The public health, housing and local government minister set out the next preparatory step in an Oct 20 State Legislative Assembly update. The plan includes a 6km Sungai Sarawak bypass, with protection expected to cover 470,233 residents and 47,264 hectares in Greater Kuching once completed. Those are future coverage estimates, not a statement that the bypass is already protecting that area.

    For residents following flood works, the engineering review is a more immediate milestone than the eventual completion window. The announcement describes preparation for construction; it is not a notice that the full Phase 2 scheme has begun operating.

    Three other packages under the Sungai Sarawak Integrated River Basin Development project are at various stages of physical implementation. Their combined RM191 million cost and target completion between the second and third quarters of 2027 belong to those packages, not to completion of the entire RM2.48 billion plan.

    The distinction matters when assessing progress around Kuching: a package finishing next year should not be mistaken for delivery of the full bypass scheme, whose stated implementation window extends to 2033.

    1 Reply Last reply
    0

    Hello! It looks like you're interested in this conversation, but you don't have an account yet.

    Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.

    With your input, this post could be even better 💗

    Register Login
    Reply
    • Reply as topic
    Log in to reply
    • Oldest to Newest
    • Newest to Oldest
    • Most Votes


    About / 关于我们Contact / 联系我们Privacy / 隐私政策Terms / 社区守则Editorial / 编辑与更正
    © 2026 KuchingHub · Independent Kuching community forum / 独立古晋社区论坛
    • Login

    • Don't have an account? Register

    • Login or register to search.
    Powered by NodeBB Contributors
    • First post
      Last post
    0
    • Categories
    • Recent
    • Tags
    • Popular
    • World
    • Users
    • Groups