  • 0 Votes
    1 Posts
    34 Views
    K
    The RM43 million Serikin Integrated Immigration, Customs, Quarantine and Security complex in Bau is 11% complete, six days ahead of schedule. Earthworks and site preparation are under way at the border facility, which is targeted for completion by the end of 2027. The complex is intended to strengthen border security and support more orderly movement between Sarawak and Indonesia. The project is being treated as an urgent national-security development rather than routine public works. Roads, electricity, water and telecommunications remain practical dependencies: a finished building could still face delays if its supporting utilities are not ready. A separate Telok Melano border control post inspected during the same working visit is still waiting for a Letter of Acceptance after final tender evaluation. Its estimated two-year construction period has not started. For southwest Sarawak, the distinction is clear: Serikin is in active construction, while Telok Melano remains before the formal award stage.
  • 0 Votes
    1 Posts
    34 Views
    K
    Four infrastructure projects are being pursued in Puncak Borneo, with a Phase 2 water-supply scheme intended to reach 18 villages. The package includes the Puncak Borneo Phase 2 water project, the RM45 million expansion of the Bengoh Resettlement Scheme, the Biya–Jabir Road project and the RM85 million SMK Puncak Borneo. Their statuses are not the same: the water scheme has faced pipeline-route objections and redesign work; the road project has recently gone out to tender; and the school has approval, funding and an identified site but is still awaiting implementation. A separate RM12.6 million acute water system in Kampung Bengoh is planned for expansion to Kampung Petag, Kampung Sitang and Kampung Bangau. The Phase 2 scheme is also planned to use Kampung Sapit as a distribution centre for Kampung Assum, Kampung Parang and surrounding areas. For Padawan residents, the immediate question is not just the size of the package but when each project moves from approval or tender into visible work.
  • 0 Votes
    1 Posts
    39 Views
    K
    A RM119 million upgrade for 17.1km of Sarawak’s Pan Borneo “redline” sections has entered a 16-month work window, with completion targeted for early 2028. The short-stretch package covers nine locations, including Lachau, Selangau, Balingian, Kemena, Sebiew and Tudan. It will upgrade pavement structures and road-safety features. The contractor received the site on Sept 17, and Sarawak JKR and the Works Ministry will monitor the work. The redline is not one continuous 17.1km route. It refers to 136.74km of sections left out of the original Pan Borneo project. The current package is the 17.1km short stretch; a separate 119.64km long stretch is still being refined for implementation. For Sarawak road users, the useful next check is how work is staged at the nine locations and whether the contractor can beat the 16-month schedule. The update did not include a detailed traffic-management timetable.
  • 0 Votes
    1 Posts
    24 Views
    K
    Twenty agricultural road projects across 20 villages in the Balai Ringin area have been grouped under a RM6 million connectivity allocation. The projects cover Zones B Jalan Simunjan and C Balai Ringin, with RM300,000 set aside for each village. The latest progress update says 16 projects are complete, two are nearing completion, one has started and one has yet to begin. The road work is intended to make it easier for farming communities to move produce and reach their plots. At Kampung Tapang Lebat, an upgraded 1.925km village road serving about 30 families was completed on June 9 at a cost of RM2.5 million. A separate community-hall store there is scheduled for next year, so the wider package should not be read as every listed project being finished.
  • 0 Votes
    1 Posts
    31 Views
    K
    Bintulu Port Sdn Bhd has been appointed the approved operator of Bintulu Port for 30 years, under a notification published in the Sarawak Government Gazette. The wholly owned Bintulu Port Holdings subsidiary’s appointment runs from Sept 1, 2026 to Aug 31, 2056. Bintulu Port Authority said the appointment was approved by the Sarawak Legislative Assembly and made under Section 12(2)(a) of the Port Authorities Ordinance 1961. The operator will continue under the terms of a Heads of Agreement until a Port Operation Concession Agreement is executed. That means the 30-year appointment is now gazetted, while the final concession document remains a separate step in the port’s operating framework. For Sarawak, the decision sets the long-term legal and operating basis for one of the state’s major ports. The next material update will be the execution of the concession agreement and its detailed conditions.
  • 0 Votes
    1 Posts
    26 Views
    K
    Bebuling Short Take-Off and Landing Airport in Spaoh, Betong has completed its first trial landing, bringing the rural facility closer to service while leaving the commercial launch date open. A Super King 300 aircraft landed at the newly completed STOLport on Friday after departing Kuching at 10am. The trial was described as smooth, but further discussions on safety, operations and maintenance must be completed before licensing and commercial operations are finalised. The RM248.03 million facility has a runway of about 1.19km and is designed to support passenger flights as well as cargo linked to agriculture and other local industries. A Kuching-Bebuling flight is expected to take about 15 minutes, compared with roughly three hours by road to Betong. The trial is therefore a readiness milestone, not an announcement of scheduled flights. The next public detail to watch is the licensing and safety approval process.
  • 0 Votes
    1 Posts
    30 Views
    K
    Sarawak is upgrading former logging roads so remote communities can reach clinics by land instead of relying on helicopter services for routine healthcare access. The road push includes routes in Baram and Marudi, with about 142 kilometres of JKR R3-standard roads and a much wider network planned statewide. Reports from DayakDaily and The Borneo Post put the broader completion target between 2030 and 2032, depending on the project scope. The policy matters beyond travel time: a road is available day and night, while air services depend on aircraft, weather and operating conditions. The state has not said that helicopters will disappear immediately. The next useful measure will be which stretches are funded, opened and connected to clinics and longhouses in each remote district.
  • 0 Votes
    1 Posts
    24 Views
    K
    A proposal to make Siburan a district has been revived as the area’s population and economic activity grow. Deputy Transport Minister Datuk Dr Jerip Susil said the proposal was first raised more than a decade ago. He said the Siburan, Tapah and Beratok areas could develop into a satellite town serving Kuching and Serian if growth is planned in an integrated way. The proposal is not an approved district upgrade. Jerip said the three areas should continue receiving attention as a more organised growth area. He also said RM5 million had been allocated to renovate and upgrade Siburan Multipurpose Hall, including work to obtain its Occupancy Permit and add parking. For communities south of Kuching, the update points to a planning direction and a confirmed hall allocation, but not a new administrative boundary or implementation timetable.
  • 0 Votes
    1 Posts
    29 Views
    K
    The RM9.89 million replacement project for SK Kampung Selanyau in Subis remains a sick project after missing its original completion date. The school site was handed over in May 2021 and was scheduled for completion in July 2022. Sarawak Education, Innovation and Talent Development Minister Datuk Seri Roland Sagah Wee Inn said during a recent visit that the project is receiving attention and that all parties must complete their responsibilities. The replacement covers classrooms, an administration building, laboratories, teachers’ quarters and other facilities. The latest report does not announce a new completion date, so the project should not be described as near completion. For the school community, the key update is that the delayed project remains under attention while the promised facilities and equipment still await completion and handover.
  • 0 Votes
    1 Posts
    36 Views
    K
    Sarawak is expected to remain a major focus for infrastructure spending when Budget 2027 is tabled next month, with the Kuching Urban Transportation System among the projects analysts are watching. A TA Securities preview says the federal government could continue funding projects that narrow the development gap, including Pan Borneo Highway phases, rural roads and bridges, port and airport upgrades, flood mitigation, water treatment and electricity networks in East Malaysia. For Greater Kuching, the report singles out KUTS as a project that could receive continued support as it moves towards commercial operations. The next phase is expected to involve not just the autonomous trains, but also feeder buses, integrated ticketing, park-and-ride facilities and passenger information systems. That is an analyst forecast, not a confirmed allocation. The Finance Ministry’s pre-budget statement identifies regional development, infrastructure delivery and stronger economic resilience as priorities, but the actual projects and amounts will only be known when the budget is presented in Parliament on Oct 9. For Kuching commuters and businesses, the useful marker is whether the final document attaches firm funding and delivery milestones to KUTS and other transport links, rather than simply repeating broad development commitments.
  • 0 Votes
    1 Posts
    33 Views
    K
    The old Batang Layar Bridge in Betong has been closed since Sept 4 and may stay shut for up to two weeks while safety repairs are carried out. Deputy Premier Datuk Amar Douglas Uggah Embas said the Public Works Department found structural concerns at the bridge. Even if the repair work finishes early, the closure may run for the full two weeks so the crossing can be checked before reopening. The replacement bridge has passed 70 per cent physical progress. The wider project, including related road works, is more than 40 per cent complete. Uggah asked the contractor to use the current dry weather to speed up construction. For people travelling through Betong, the confirmed position is simple: the old crossing is not yet open, and the new bridge is still a construction project. Follow the latest local traffic notice before choosing the route; no reopening date was announced in the report.
  • 0 Votes
    1 Posts
    28 Views
    K
    RM5.8 million project to light up 11.9km Petra Jaya-Rambungan route, completion set for June 2027 A RM5.8 million street lighting project along the 11.9-kilometre Petra Jaya–Rambungan route has been handed over for implementation, with completion targeted by June 16, 2027. Sarawak Deputy Minister in the Premier's Department Datuk Dr Abdul Rahman Junaidi said the project will install and rehabilitate high- and low-voltage systems along the route, particularly in the Matang section. The work includes 11kV overhead lines with six 50kVA transformers and 794 LED street lights, along with underground cabling, mini pillars and control boxes. Dr Abdul Rahman said vandalism had been a recurring problem — this is roughly the fifth time lighting has been reinstalled along this road — and called for closer community cooperation to monitor and report suspicious activity. The road serves as a main route and an alternative to Jalan Matang, with usage rising alongside nearby housing development. The project connects the Pantai Damai and Tupong state constituencies. The contractor is Arena Megasuria Sdn Bhd, with Perunding Teknikal Consult Sdn Bhd as consultant and the Kuching Division Public Works Department as superintending officer.
  • 0 Votes
    1 Posts
    21 Views
    K
    MBKS is preparing a 200-metre reinforced-concrete box drain to improve flood protection along Jalan Padungan and Jalan Chan Chin Ann. The proposed drain would measure 1.2 metres wide and 1.2 metres deep. Survey work, possible utility relocation, road and footpath reinstatement, plus traffic and safety arrangements are part of the plan. The two roads and nearby Jalan Abell area have recurring flash floods during intense rain. MBKS said the existing network cannot handle high stormwater volumes easily, but work in this built-up city-centre area must be designed around businesses, roads and underground services. The project is not at construction stage yet. A consultant must first complete the plans and technical documents before MBKS starts the tender process. Drivers and businesses should expect temporary traffic arrangements only when work eventually begins.
  • 0 Votes
    1 Posts
    24 Views
    K
    Stampin Resettlement Scheme’s flood project now has a contractor, but residents are still waiting for the construction timetable. DID Sarawak handed the Letter of Award to TMK Construction and Transport Sdn Bhd on Sept 2. The first package, valued at RM87,956,231.16, covers roadside drains and culverts along Jalan Stampin Baru and work on outlets leading to Sungai Stampin, Sungai Stutong and Sungai Kuap. This is the first firm step towards site work after years of planning. A DID update in July said the RM350 million scheme was announced in November 2022 and had yet to begin physical construction at that point. The wider plan will be delivered in stages, with reinforced-concrete drains, channels and detention ponds among the proposed works. Project estimates put the reach at 1,053 households, or 9,026 people. The award does not mean flood protection is already in place. DID has not published the start and completion dates or a traffic-management schedule, details that Jalan Stampin Baru residents will need once work begins.
  • 0 Votes
    1 Posts
    31 Views
    K
    Work has begun on a RM2.1 million Sungai Kayan riverbank project in Kampung Krusen Kranji, eight months after heavy rain triggered a landslide that cut the village’s main access road. The Sept 2 site handover starts a 12-month construction period ending Sept 1, 2027. The Sarawak State Disaster Management Committee is funding the job, while the Drainage and Irrigation Department’s Serian office is responsible for implementation and monitoring. The January landslide also damaged a suspension bridge at Kampung Krusen Siu. Authorities warned residents then not to use it; its RM900,000 replacement is still at final document-assessment stage and has no announced start date. Four smaller allocations have also been approved: RM150,000 for solar power in three Krusen villages, RM100,000 each for the Kampung Krusen Mawang community hall and village road, and RM280,000 for the Awah Gawai facility in Krusen Siu. Their schedules have not been announced.
  • 0 Votes
    1 Posts
    25 Views
    K
    The RM170 million Menalun–Sungai Poi road project in Kanowit is moving into Phase 3, but the full route is still targeted for completion only in 2030. Phases 1 and 2 have been completed. The latest phase began with a groundbreaking on Aug 29 and involves a 3.6-kilometre road through hilly terrain. It carries an allocation of RM46.11 million and a contract value of RM39.96 million, and does not include bridges or extend as far as the school. Phase 4 remains at the design stage. The RM58.4 million allocation covers another 2.6 kilometres and two bridges, with the planned route connecting Sekolah Kebangsaan Ulu Poi and the longhouses Rumah Panjang Gani and Rumah Panjang Tarang. The project is meant to improve access for remote communities and essential services, but the 2030 date is a completion target that depends on the remaining phases being delivered. The road should not be treated as a fully open connection yet; the next milestones are Phase 3 progress and a firm construction plan for Phase 4.
  • 0 Votes
    1 Posts
    25 Views
    K
    Bintulu Port will come under Sarawak management on Sept 1 after a three-year handover process. The change follows the Bintulu Port Authority (Dissolution) Act 2024 taking effect on Aug 31. The transition covered staff, assets, finances and legal matters. The completed arrangements cover the absorption of all BPA employees, the return of some assets to Sarawak and settled compensation for transferred port assets. Bintulu Port has grown from an energy-industry facility into a major trade and LNG gateway over 47 years. The handover changes its jurisdiction and administration; the reports do not announce a port closure. Sarawak's plan to integrate it with the state's other ports, along with any changes port users may see, has not yet been detailed.
  • 0 Votes
    1 Posts
    30 Views
    K
    Sarawak approves RM6 million road to Nanga Kapu in Batang Ai Sarawak has allocated RM6 million to build a road to Nanga Kapu, with the announcement made at the Batang Ai Community Engagement Programme in Lubok Antu on Aug 28. The project is intended to improve access for remote residents travelling to essential services and economic opportunities. The announcement did not include the road’s length, final route or a construction timetable, so the funding is not yet an indication that a new road is open for use. The next milestones are the design work, tender and appointment of a contractor. The construction schedule will become clearer once those steps are completed.
  • 0 Votes
    1 Posts
    42 Views
    K
    Long Banga and Ba’kelalan STOLports will share RM30 million in federal funding for upgrades targeted to start this year. Each rural airstrip has been allocated RM15 million from the Airport Development Fund. The money is approved, but design work and other preparations must be completed before construction can begin. The plans cover terminal improvements and possible runway extensions, depending on the physical conditions at each site. The current runway limits Twin Otter flights to nine passengers; a longer runway could raise that capacity, although the final scope is still being worked out. For communities in Sarawak’s northern interior, the two air links support access to schools, healthcare, supplies and town services across difficult terrain. The next concrete milestones are the design work, the construction schedule and a decision on whether either runway can be extended. Location: Long Banga and Ba’kelalan, Sarawak
  • 0 Votes
    1 Posts
    23 Views
    K
    A completed booster-pump upgrade is easing long-running water-pressure problems in four villages in Bau’s Singai area. The RM3 million project doubled the Kampung Apar suction tank’s capacity from 50,000 to 100,000 gallons. Five new high-density polyethylene tanks were installed, and a new pipeline now carries water to the reservoir at Kampung Barieng, serving Kampung Apar, Kampung Segong, Kampung Barieng and Kampung Tabung. The pump has been commissioned and handed over to the Sarawak Rural Water Supply Department. The upgrade was aimed at homes on higher ground, where the old system struggled to maintain pressure as the villages expanded. Another RM8 million project to lay a 300mm HDPE pipeline in Jagoi is nearing completion. Additional booster pumps are planned for Kampung Bobak and Kampung Senibung, but no dates have been given for those installations. Residents have already seen an improvement during this year’s prolonged dry spell. The next test will be whether the pressure stays reliable through the dry season and the higher demand during festive periods. Location: Singai, Bau