  4. Sarawak's First Road Tunnel at Bukit Pagon, Lawas — SSLR Phase 2 Hits 11.39% Progress

Sarawak's First Road Tunnel at Bukit Pagon, Lawas — SSLR Phase 2 Hits 11.39% Progress

Scheduled Pinned Locked Moved News 📰
kuching-newssarawakinfrastructuretunnelsslr
1 Posts 1 Posters 13 Views 1 Watching
  • Oldest to Newest
  • Newest to Oldest
  • Most Votes
Reply
  • Reply as topic
Log in to reply
This topic has been deleted. Only users with topic management privileges can see it.
  • K Offline
    K Offline
    kuchinghub
    wrote last edited by
    #1

    Sarawak is building its first-ever road tunnel — a 2.24km underground passage through Bukit Pagon in Lawas, cutting travel distance from 22.4km to just 7km.

    The tunnel is part of the Sarawak–Sabah Link Road (SSLR) Phase 2, a 335.54km road alignment connecting Sarawak and Sabah. As of June 11, Phase 2 has reached 11.39% physical progress, with full completion targeted for 2029.

    📍 Location: Bukit Pagon, Bakun Range (Lawas–Limbang border)
    📰 Details:

    • 2.24km tunnel under Package 4 of SSLR Phase 2
    • Cuts travel distance from 22.4km to 7km — saving over 15km
    • 2% longitudinal gradient, 321m max overburden depth
    • Emergency widening sections every 500m for safety
    • Expected to significantly improve connectivity between Sarawak and Sabah

    JKR Sarawak director Datu Dr Ir Cassidy Morris visited the tunnel site on June 11 to inspect progress.

    Meanwhile, SSLR Phase 1 has reached 71.16% completion and is on track for March 16, 2027. It features the MyArch Bridge, a modern arch bridge design that will serve as a landmark along the route.

    Phase 2 Package 3 (62.9km road built to JKR R3 standards) is also progressing at 16.25%, targeting completion by June 2029.


    The proposed tunnel location at Bukit Pagon, Lawas


    MyArch Bridge — a landmark design feature of SSLR Phase 1

    🔗 Source: DayakDaily

    What do you think of Sarawak's first tunnel? 👇

    1 Reply Last reply
    0

    Hello! It looks like you're interested in this conversation, but you don't have an account yet.

    Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.

    With your input, this post could be even better 💗

    Register Login
    Reply
    • Reply as topic
    Log in to reply
    • Oldest to Newest
    • Newest to Oldest
    • Most Votes


    • Login

    • Don't have an account? Register

    • Login or register to search.
    Powered by NodeBB Contributors
    • First post
      Last post
    0
    • Categories
    • Recent
    • Tags
    • Popular
    • World
    • Users
    • Groups