  4. Kampung Sageng riverbank works reach 24.95%, well behind September target

Kampung Sageng riverbank works reach 24.95%, well behind September target

Scheduled Pinned Locked Moved News 📰
simunjansarawakinfrastructureriverbank
1 Posts 1 Posters 44 Views 1 Watching
  • Oldest to Newest
  • Newest to Oldest
  • Most Votes
Reply
  • Reply as topic
Log in to reply
This topic has been deleted. Only users with topic management privileges can see it.
  • K Offline
    K Offline
    kuchinghub
    wrote last edited by
    #1

    The RM40.8 million riverbank protection project at Kampung Sageng in Simunjan had reached 24.95% completion on Sept 25, against a scheduled 68.77%. That leaves a gap of 43.82 percentage points—not 43.82% of work that has been cancelled.

    The project covers 968 metres of riverbank protection intended to reduce erosion risks near residential settlements. After inspecting it on Sept 29, Batang Sadong MP Rodiyah Sapiee asked the contractor for a clear recovery plan. Technical adjustments prompted by actual river conditions were cited as a factor in the slower progress.

    A separate scheme, the RM22.34 million Simunjan Flood Mitigation Plan Phase 1, was further along at 70.09% on the same reporting date. That scheme covers a wider drainage and flood-control package: drainage upgrades, a retention pond, deepening Sungai Kelka and tidal control gates.

    April 2027 was given as the expected completion for that flood-mitigation scheme, subject to an extension-of-time decision. It was not announced as a fixed completion date for the Kampung Sageng riverbank project.

    For residents, the two progress figures should not be mixed together: one concerns protection along a particular stretch of riverbank, while the other covers a separate flood-mitigation system. The next update that matters is the riverbank contractor’s recovery programme and whether the remaining flood-control work meets its revised timetable. Neither reported percentage means the full protection is already in place.

    1 Reply Last reply
    0

    Hello! It looks like you're interested in this conversation, but you don't have an account yet.

    Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.

    With your input, this post could be even better 💗

    Register Login
    Reply
    • Reply as topic
    Log in to reply
    • Oldest to Newest
    • Newest to Oldest
    • Most Votes


    About / 关于我们Contact / 联系我们Privacy / 隐私政策Terms / 社区守则Editorial / 编辑与更正
    © 2026 KuchingHub · Independent Kuching community forum / 独立古晋社区论坛
    • Login

    • Don't have an account? Register

    • Login or register to search.
    Powered by NodeBB Contributors
    • First post
      Last post
    0
    • Categories
    • Recent
    • Tags
    • Popular
    • World
    • Users
    • Groups