‘Last Miles’ Projects to Bring Power to 147 Ngemah Households
-
Two rural electrification projects worth RM13.1 million are being implemented in Ngemah to connect 147 households.
The projects cover Ngemah Tengah and Hulu Ngemah. Ngemah assemblyman Anyi Jana said the RM9.188 million Phase 3 project in Ngemah Tengah is 66.6% complete and will benefit 114 households in four longhouses and one settlement.
Electricity has already reached 65 households. The remaining homes are at Rumah Lau, Rumah Ai and Rumah Reba. Power-line works for the three longhouses are targeted for completion by the end of this year, with documentation expected to be submitted to Recoda on Aug 21.
The RM3.909 million Phase 4A project in Hulu Ngemah is 9.4% complete. It will cover two longhouses and 33 households, with completion targeted for December 2027. Rain, difficult access and the use of logging roads remain challenges.
The update is still developing; residents should rely on the next confirmed notice rather than treat an early announcement as final.

Source: Pusat Khidmat Masyarakat Ngemah / The Borneo Post
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login