Jalan Ilmu in Miri to be raised by half a metre as flood repairs begin
The low-lying road in Desa Senadin is now undergoing a RM1.481 million upgrade after it was badly affected by flooding earlier this year.
Work runs from Aug 11 to Dec 10 and includes 510 metres of road-base work, 1,245 metres of premix, concrete kerbs, road shoulders and new markings. Raising the road level by about half a metre is intended to reduce the risk of repeated inundation.
Miri’s wider road recovery will take longer. A separate RM10 million package covers 20 roads—seven in Desa Senadin, eight in Permyjaya and five in Tudan. Tenders are expected in the first or second week of September, with work targeted for October.
Jalan Ilmu has a live construction schedule; the other roads are still awaiting tender. Motorists in the area should expect work-zone conditions while the projects progress.
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login