Contractor Appointed for Long-Awaited RM350m Stampin Flood Project
-
Stampin Resettlement Scheme’s flood project now has a contractor, but residents are still waiting for the construction timetable.
DID Sarawak handed the Letter of Award to TMK Construction and Transport Sdn Bhd on Sept 2. The first package, valued at RM87,956,231.16, covers roadside drains and culverts along Jalan Stampin Baru and work on outlets leading to Sungai Stampin, Sungai Stutong and Sungai Kuap.
This is the first firm step towards site work after years of planning. A DID update in July said the RM350 million scheme was announced in November 2022 and had yet to begin physical construction at that point. The wider plan will be delivered in stages, with reinforced-concrete drains, channels and detention ponds among the proposed works. Project estimates put the reach at 1,053 households, or 9,026 people.
The award does not mean flood protection is already in place. DID has not published the start and completion dates or a traffic-management schedule, details that Jalan Stampin Baru residents will need once work begins.
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login