Sarawak Stadium Upgrade Hits 22.55% — All SEA Games 2027 Venues on Track for Q1 Completion
-
Sarawak Stadium upgrade hits 22.55% — all SEA Games venues on track for Q1 2027 completion
{img0}
Sarawak's preparations for the 2027 SEA Games are picking up pace. JKR Sarawak director Datu Ir Cassidy Morris inspected several sports venues on Aug 11, and the numbers look solid.
Sarawak Stadium's upgrading and refurbishment has reached 22.55% progress, targeted for completion in January 2027 — well ahead of the SEA Games in September.
Other venues also progressing:
- Stadium Perpaduan: 13.31%, completion Feb 2027
- Lawn Bowl Arena: completion Jan 2027
- Wushu Training Centre: completion Feb 2027
- SLTA complex: completion March 2027
Cassidy stressed that all projects must be completed on time without compromising quality and safety. The Q1 2027 timeline leaves enough room for testing and final inspections before the Games.
Location: Kuching, Sarawak
Details: Sarawak Stadium 22.55% done; 5 venues being upgraded; all targeted for Q1 2027
Source: DayakDailyGetting ready for SEA Games 2027 — are you excited?

Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login