砂拉越Menalun—Sungai Poi道路计划目标2030年完成
-
砂拉越Kanowit的Menalun—Sungai Poi道路计划进入第三期,但全线目标要到2030年才完成。
这项总值1亿7000万令吉的工程分四期进行,首两期已经完成,第三期在8月29日举行动工仪式。第三期将建设一条全长3.6公里、经过丘陵地形的道路,拨款4611万令吉,合约价值3996万令吉;这一路段不涉及桥梁,也不会延伸至学校。
第四期目前仍在设计阶段,获拨款5840万令吉,计划建设2.6公里道路和两座桥梁,连接Sekolah Kebangsaan Ulu Poi,以及Rumah Panjang Gani和Rumah Panjang Tarang两座长屋。
工程完成后可改善偏远社区和基本服务的交通联系,不过2030年是全线完工目标,仍取决于剩余阶段的落实。现阶段不能把这条道路视为已经全线开放,接下来应留意第三期进度,以及第四期何时确定施工安排。
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.